Link to ROC Facebook Link to Twitter Link to Youtube    Skip Navigation Links
About The ROC
Field Requirements BranchExpand Field Requirements Branch
EngineeringExpand Engineering
OperationsExpand Operations
Program BranchExpand Program Branch
Current WeatherExpand Current Weather
Level I Data
Level II Data
Level III Data
Related LinksExpand Related Links
ROC Papers
Safety &
Environmental
Expand Safety &<br> Environmental
Site ID / MapsExpand Site ID / Maps
Software Build InformationExpand Software Build Information
SPG
Wind ProfilerExpand Wind Profiler
System
Documentation
Expand System<br>Documentation
WSR-88D ProgramExpand WSR-88D Program
Questions & Comments
 

Pedestal Refurbishment




  • The Plan:
    • Full-Service Contract to cover entire spectrum of tasks
    • Field Process
      • Remove Pedestal from tower (requires radome/antenna removal)
      • Replace Pedestal with remanufactured pedestal
      • Re-install antenna and radome
      • Test System
      • Ship old pedestal to remanufacturing facility
    • Pedestal Remanufacturing
      • Complete tear down
      • Inspect/Test wear components and replace as required
      • Rebuild pedestal to OEM specifications
      • Factory acceptance test
      • Ship remanufactured pedestal as directed
  • Limitations of a Round Robin approach:
    • Only 4 spare pedestals (3 FSP and 1 LPP)
    • Spares are seed stock for round robin process




Pedestal Hoisting Pedestal




Failed Bearings Cause Catastrophic Pedestal Failure
Current Signal Processor Architecture